Sunday Monday Tuesday Wednesday Thursday Friday Saturday

29

JD88

30

JD89

31

JD90

1

JD91
Site Visit (SpB, NT, SL): Details , Photos (21)

Span cylinder at 800 psi. N2 at 600 psi.

between 9:30-10:00 MST, rebooted russter2, checked BIOS.

Overcast, mostly calm. A few inches of fresh snow.

2

JD92

3

JD93
SpB off (half-day)

4

JD94

5

JD95

6

JD96
SpB (working from afar for entire week)

7

JD97

8

JD98

9

JD99

10

JD100

11

JD101

12

JD102

13

JD103

14

JD104

15

JD105
bring stuff to replace fittings in profiler. and bring BATTERY from lab!!

16

JD106
SpB back at work

17

JD107
Power Outage from around 12:00-15:30

russter2 does not come back up after outage...

BIG upslope snowstorm.

18

JD108
Power Outage most of Friday night till Saturday afternoon (around 15:00 MST)

(surprisingly, russter2 reboots itself; but quacker is down)

snowstorm continues.

19

JD109
Site Visit (SpB): Details , Photos (27)

Span cylinder at 600 psi.

at ~13:00 MST, rebooted quacker, restarted data system (FAST cr23x logger took a bit of coaxing to get working again).

from 14:00-16:00 MST, switched N2 cylinder at the tower (new cylinder=CC198519 (1900 psi); old cylinder=CC264970 (0 psi))

Bright and sunny. About 3 feet of new (wet) snow.

20

JD110

21

JD111

22

JD112

23

JD113

24

JD114
Site Visit (SpB, NT): Details , Photos (32)

Span cylinder at 600 psi. N2 at 1820 psi.

at 10:45 MST, re-adjusted ht of 2m profile inlet from 1.2m back up to 2m.

at 11:00 MST, power-cycled 2.56m csat to get it working again

from 12:12-13:25 MST, Changed profiler (li-6251) dessicant + adjusted li-6262 flows

at 13:50 MST, swiped the kyrpton hyg

Partly cloudy and warm. Blustery at times, but calm in the afternoon.

25

JD115

26

JD116
Power Outage from around 10:30-13:30 MST

russter2 goes down (and stays down). data system shuts down.

27

JD117
Site Visit (JK): Details

at ~9:35 MST, John Knowles (CU) reboots russter2

at ~9:50 MST, restarted ndaq on quacker, things look ok.

28

JD118

29

JD119

30

JD120

1

JD121

2

JD122
Power Outage at C-1 from around 14:00-15:20 MST

russter2 goes down (and stays down). data system shuts down.