Sunday | Monday | Tuesday | Wednesday | Thursday | Friday | Saturday |
26JD177 |
27JD178Site Visit (SpB, NT, DB, E, B): Details , Photos (28) Span cylinder at 1190 psi. N2 at 1100 psi Tref in am25t "A" connected to TC logger is way off (need to look into this, when did problem start?) from 11:15-11:50 MST, moved P sensor "B8" from 21.5m to near the ground from approx 12:12-12:32 MST, Changed profiler (li-6251) dessicant Cool and breezy in morning, cleared up, then clouded up again in afternoon. Snow is gone, creek is high. CU Jeep DB at site (entire week) |
28JD179at around 9:00 MDT, ati k-probe stops working. |
29JD180 |
30JD181 |
1JD182 |
2JD183 |
3JD184 |
4JD185Independence Day |
5JD186 |
6JD187 |
7JD188 |
8JD189Site Visit (SpB, NT, E, B): Details , Photos (37) Span cylinder at 1100 psi. N2 at 890 psi at approx 10:00 MST, power-cycled the ATI k-probe (this fixed the problem) at approx 10:30 MST, modified orientation of krypton hygrometer from 11:00-11:40 MST, removed eol P sensors and data system from 13:50-14:15 MST, replaced 3 lowest inlet filters for co2 profile system Sunny in morning, threat of rain, then cleared up, then clouded up again in afternoon. CU Suburban |
9JD190Stardot camera and forestcam both off-line (problem with black box fiber-to-copper converter) |
10JD191Short power outage (Sun Jul 10 14:19:06 MDT 2011, 152 seconds) |
11JD192 |
12JD193 |
13JD194 |
14JD195at around 15:30 MST, power outage at the site; data system down |
15JD196Site Visit (SpB): Details , Photos (14) Span cylinder at 1010 psi. N2 at 700 psi from 11:10-11:40 MST, replaced domes on REBS 25.5m Rnet sensor network problem to forestcam is due to a network converter failure (see notes) Sunny and warm. Some Cu in the afternoon. CU Prius |
16JD197 |
17JD198Short power outage (2011-07-17 15:48:22 -0600, 5 seconds) ati k-probe stops working (again?). |
18JD199Start of the NSF "Flux" class at MRS. |
19JD200Short power outage (2011-07-19 13:46:07 MDT, 10 seconds) ati k-probe starts working (probably due to power reset). |
20JD201 |
21JD202Site Visit (SpB, RM, + flux class): Details , Photos (11) Span cylinder at 1000 psi. N2 at 590 psi |
22JD203 |
23JD204SpB Off |
24JD205 |
25JD206 |
26JD207 |
27JD208At approx mid-day, the 1.6m 2-D handar stops working |
28JD209 |
29JD210End of the NSF "Flux" class at MRS. |
30JD211SpB Returns |
31JD212 |
1JD213 |
2JD214Site Visit (SpB, E, B): Details , Photos (29) Span cylinder at 900 psi. N2 at 200 psi --> 1700 psi From 10:15-10:30 MST, swapped N2 cylinder; old=cc302236, new=cc301525 from approx 9:33-9:50 MST, Changed profiler (li-6251) dessicant At approx 10:30 MST, fixed thermocouple T7 (3rd level AGL). At approx 10:45 MST, swiped krypton hygrometer Cool and cloudy, some rain. Supposed to be a BIG storm (that never happened) CU Prius |
3JD215SpB to SPL |
4JD216SpB to SPL SPL photos |
5JD217 |
6JD218 |